Guide
Bathroom renovation work stages
The stages of a bathroom renovation from brief to handover, the hold points where testing happens before finishes, and the decisions due at each stage.
By the Classic Apex team · Updated 22 October 2026 · About 5 minutes to read · For homeowners and landlords planning a bathroom refurbishment
A bathroom renovation packs plumbing, drainage, electrical work, waterproofing, tiling and fittings into a small room, in a fixed order. Each stage depends on the one before it, and some work is hidden for good once tiles go on. Understanding the stages helps you plan decisions, approvals and time away from the room, and know which checks matter most.
The sequence below describes a full refurbishment. A smaller refresh skips some stages, which is fine as long as everyone agrees which ones are included.
Before work starts
1. Brief and assessment
Write down what is wrong with the current bathroom and what you want from the new one: layout, storage, shower or bath, and any leaks or damp you have noticed. The assessment looks at the room, the drainage routes, the condition of visible pipes and finishes, and the access available. Measurements and photographs are taken at this stage.
2. Scope and specification
The quotation should set out what is removed, what is renewed and what stays. This includes the extent of waterproofing, whether the floor screed is renewed, any changes to fixture positions, electrical items such as lighting and the extract fan, and ceiling works. The guide to clarifying waterproofing in a bathroom quote covers the questions that matter most here.
3. Selections and sign-off
Tiles, sanitaryware, taps and mixers, shower screen, vanity, mirror and accessories should be chosen and confirmed before strip-out. Concealed shower valves and wall-hung toilet frames, in particular, must be known before walls are closed. Long lead items should be ordered early.
4. Approvals and scheduling
In apartments, check with building management whether approval, a work permit or set working hours apply, and how debris must be removed. Tenants need owner approval. Agree the start date, working hours and whether another bathroom is available while this one is out of use.
Strip-out and concealed work
5. Protection and isolation
The route from the entrance to the bathroom is protected, and water and power to the room are isolated as needed. Neighbouring rooms may need dust protection.
6. Strip-out
Old tiles, fixtures, and where specified the screed and waterproofing, are removed. This is when hidden conditions appear: corroded pipes, damaged waste connections, loose substrate, or signs of previous leaks.
7. Inspection of exposed conditions
The exposed walls, floor and pipework are checked against the plan. If concealed defects are found, they should be explained, photographed and quoted for your approval before work continues. Agreeing this process in advance avoids disputes later.
8. First fix plumbing and electrical
New or altered supply and waste pipes, concealed valves, wall-hung toilet frames and electrical cabling are installed. Positions are set out from the selected fixtures.
9. Testing before concealment
This is a key hold point. Supply pipework and connections should be tested in a way appropriate to the work before they are hidden, and drainage checked for flow. Ask how this will be done and whether you will see the result or receive a photograph.
Building up the finishes
10. Screed and falls
Where the floor is renewed, the screed is laid with falls towards the drain, especially in the shower area. Falls are difficult to correct once tiled, so this deserves attention.
11. Waterproofing and testing
The waterproofing system is applied to the specified areas and allowed to cure according to the product instructions. Where a water test is part of the specification, it takes place before tiling. This is the second key hold point.
12. Tiling
Wall and floor tiles are laid, grouted and finished at edges and junctions. The guide to tile considerations for wet areas explains what to think about when choosing tiles for showers and floors.
13. Second fix and fittings
Toilet, basin, vanity, taps, shower fittings, screen, mirror, accessories, lights and fan are fitted and connected. Silicone sealant is applied at junctions where specified.
Completion and handover
14. Checks, cleaning and snagging
Fixtures are checked for flow, drainage and visible leaks, lights and fans are tested, and the room is cleaned. Walk through the room with the person in charge and list any snags: chipped tiles, uneven grout, loose fittings, or gaps in sealant.
15. Handover
You should receive any manufacturer documentation for fittings, details of the products used, care guidance for finishes and sealant, and written warranty terms where these are offered.
If you are planning a smaller refresh
Not every bathroom needs the full sequence. If the tiles, falls and waterproofing are sound and there is no sign of leaks, a refresh might replace sanitaryware, taps, the vanity, the mirror and lighting, with regrouting and new sealant. In that case stages 6 to 11 shrink or disappear, and the work moves quickly from protection to second fix.
The important point is to be clear about what a refresh does not include. New fixtures on top of old waterproofing will not cure an existing leak, and tiling over old tiles changes floor levels at the door and around the drain. If you are unsure whether the existing build-up is sound, ask for the assessment to look at it specifically before you decide between a refresh and a full renovation.
Hold points and decisions at a glance
| Stage | Your decision or check |
|---|---|
| Scope and specification | Confirm extent of waterproofing, screed and position changes |
| Selections | Sign off all fixtures and finishes, order long lead items |
| Approvals | Building permission, working hours, debris removal |
| Exposed conditions | Approve or decline any additional work found at strip-out |
| Testing before concealment | Confirm pipework testing has taken place |
| Waterproofing | Confirm curing and any specified water test before tiling |
| Snagging | Agree the snag list and when it will be cleared |
How long each stage takes depends on scope, product curing times, approvals and materials, and is confirmed after assessment.
Next step
Use the bathroom planning checklist to record your selections and the stages you want included. Then share it with photographs through the bathroom renovation service page so the assessment can confirm the scope and programme.